Project Status Overview: July 2005 - June 2008
Completed:
In Progress:
Phase III
| Status Overview | Scope | Kick-Off | Planning | Design | Development | Testing | Implementation | Production |
|---|---|---|---|---|---|---|---|---|
| GALILEO Upgrade Project | completed | completed | completed | in progress | in progress | in progress | in progress | |
| Sub-Project: Community Portal Customizations | completed | completed | completed | completed | completed | completed | completed | completed |
| Sub-Project: Courseware/Website Integration | completed | completed | completed | in progress | in progress | |||
| Sub-Project: MetaLib | completed | completed | completed | in progress | in progress | in progress | in progress |