Previously Completed Tasks:

1. Draft project scope document.   (DONE)

2. Distribute to project team and other stakeholders.  (DONE)

3. Critical Issues session on project scope document.  (DONE)

4. Revise project scope document.  (DONE)

5. Distribute to project team and other stakeholders.  (DONE)

 

Newly Completed Tasks: 

6. Review and revise VPAC recommendations in light of Counter. (DONE --no change.)

8. Get sample report from EBSCO as first target and review with programmers.  (DONE)

9. Identify targeted vendors and develop general steps for each product to be captured.  Develop tracking mechanism for monitoring progress. (DONE)

 

In Progress Tasks:

7. Review what other national consortia are doing for collection and presentation of usage statistics and determine if their efforts can be leveraged or adopted.  (IN PROGRESS -- the few things that are out there for review have been identified.)

10. Complete steps 9a-h for resources 9i-xx.  (IN PROGRESS:  EBSCO, ProQuest)

11. Develop plan and steps for archival collection/storage for each product. Develop tracking mechanism for monitoring progress.  (IN PROGRESS)

12. Draft Communication plan. (IN PROGRESS)

 

 

LF 6/6/03