Previously
Completed Tasks:
1. Draft project
scope document. (DONE)
2. Distribute to
project team and other stakeholders.
(DONE)
3. Critical
Issues session on project scope document.
(DONE)
4. Revise project
scope document. (DONE)
5. Distribute to
project team and other stakeholders.
(DONE)
Newly Completed
Tasks:
6. Review and
revise VPAC recommendations in light of Counter. (DONE --no change.)
8. Get sample
report from EBSCO as first target and review with programmers. (DONE)
9. Identify
targeted vendors and develop general steps for each product to be
captured. Develop tracking
mechanism for monitoring progress. (DONE)
In Progress
Tasks:
7. Review what
other national consortia are doing for collection and presentation of usage
statistics and determine if their efforts can be leveraged or adopted. (IN PROGRESS -- the few things that are
out there for review have been identified.)
10. Complete
steps 9a-h for resources 9i-xx.
(IN PROGRESS: EBSCO,
ProQuest)
11. Develop plan
and steps for archival collection/storage for each product. Develop tracking
mechanism for monitoring progress.
(IN PROGRESS)
12. Draft
Communication plan. (IN PROGRESS)
LF 6/6/03