HRMS 7.51 Upgrade- Rollout Schedule
Project Start Date: Thu 8/17/00
Project Finish Date: Fri 9/7/01
| Production Release | Mon 6/11/01 | Fri 9/7/01 |
| Fileserver Components Packaging | Mon 6/11/01 | Fri 6/15/01 |
| Workstation Components Packaging | Mon 6/11/01 | Fri 6/15/01 |
| Fileserver/Workstation Component Testing | Mon 6/18/01 | Fri 6/29/01 |
| Production Release Pilot - GPC (710) | Mon 7/2/01 | Fri 7/6/01 |
| Build | Mon 7/2/01 | Fri 7/6/01 |
| Verify | Mon 7/2/01 | Fri 7/6/01 |
| Sign-off | Mon 7/2/01 | Fri 7/6/01 |
| Pilot Live | Fri 7/6/01 | Fri 7/6/01 |
| Begin Production Support | Mon 7/2/01 | Mon 7/2/01 |
| Biweekly Payroll | Sat 7/7/01 | Tue 7/10/01 |
| Production Release Clusters | Mon 7/2/01 | Fri 9/7/01 |
| Production Release Cluster 1 | Mon 7/2/01 | Sat 7/14/01 |
| Fileserver Components Packaging | Mon 7/2/01 | Fri 7/6/01 |
| Workstation Components Packaging | Mon 7/2/01 | Fri 7/6/01 |
| Southern (390) | Wed 7/11/01 | Sat 7/14/01 |
| Build | Wed 7/11/01 | Sat 7/14/01 |
| Verify | Wed 7/11/01 | Sat 7/14/01 |
| Sign-off | Wed 7/11/01 | Sat 7/14/01 |
| Follow-up | Sat 7/14/01 | Sat 7/14/01 |
| Institution Live | Sat 7/14/01 | Sat 7/14/01 |
| Savannah (480) | Wed 7/11/01 | Sat 7/14/01 |
| Build | Wed 7/11/01 | Sat 7/14/01 |
| Verify | Wed 7/11/01 | Sat 7/14/01 |
| Sign-off | Wed 7/11/01 | Sat 7/14/01 |
| Follow-up | Sat 7/14/01 | Sat 7/14/01 |
| Institution Live | Sat 7/14/01 | Sat 7/14/01 |
| Armstrong (240) | Wed 7/11/01 | Sat 7/14/01 |
| Build | Wed 7/11/01 | Sat 7/14/01 |
| Verify | Wed 7/11/01 | Sat 7/14/01 |
| Sign-off | Wed 7/11/01 | Sat 7/14/01 |
| Follow-up | Sat 7/14/01 | Sat 7/14/01 |
| Institution Live | Sat 7/14/01 | Sat 7/14/01 |
| West Georgia (540) | Wed 7/11/01 | Sat 7/14/01 |
| Build | Wed 7/11/01 | Sat 7/14/01 |
| Verify | Wed 7/11/01 | Sat 7/14/01 |
| Sign-off | Wed 7/11/01 | Sat 7/14/01 |
| Follow-up | Sat 7/14/01 | Sat 7/14/01 |
| Institution Live | Sat 7/14/01 | Sat 7/14/01 |
| Production Release Cluster 2 | Mon 7/9/01 | Fri 7/20/01 |
| Fileserver Components Packaging | Mon 7/9/01 | Fri 7/13/01 |
| Workstation Components Packaging | Mon 7/9/01 | Fri 7/13/01 |
| Valdosta (510) | Tue 7/17/01 | Fri 7/20/01 |
| Build | Tue 7/17/01 | Fri 7/20/01 |
| Verify | Tue 7/17/01 | Fri 7/20/01 |
| Sign-off | Tue 7/17/01 | Fri 7/20/01 |
| Follow-up | Fri 7/20/01 | Fri 7/20/01 |
| Institution Live | Fri 7/20/01 | Fri 7/20/01 |
| ABAC (570) | Tue 7/17/01 | Fri 7/20/01 |
| Build | Tue 7/17/01 | Fri 7/20/01 |
| Verify | Tue 7/17/01 | Fri 7/20/01 |
| Sign-off | Tue 7/17/01 | Fri 7/20/01 |
| Follow-up | Fri 7/20/01 | Fri 7/20/01 |
| Institution Live | Fri 7/20/01 | Fri 7/20/01 |
| Coastal (630) | Tue 7/17/01 | Fri 7/20/01 |
| Build | Tue 7/17/01 | Fri 7/20/01 |
| Verify | Tue 7/17/01 | Fri 7/20/01 |
| Sign-off | Tue 7/17/01 | Fri 7/20/01 |
| Follow-up | Fri 7/20/01 | Fri 7/20/01 |
| Institution Live | Fri 7/20/01 | Fri 7/20/01 |
| Waycross (890) | Tue 7/17/01 | Fri 7/20/01 |
| Build | Tue 7/17/01 | Fri 7/20/01 |
| Verify | Tue 7/17/01 | Fri 7/20/01 |
| Sign-off | Tue 7/17/01 | Fri 7/20/01 |
| Follow-up | Fri 7/20/01 | Fri 7/20/01 |
| Institution Live | Fri 7/20/01 | Fri 7/20/01 |
| Biweekly Payroll | Sat 7/21/01 | Tue 7/24/01 |
| Production Release Cluster 3 | Mon 7/16/01 | Sat 7/28/01 |
| Fileserver Components Packaging | Mon 7/16/01 | Fri 7/20/01 |
| Workstation Components Packaging | Mon 7/16/01 | Fri 7/20/01 |
| North Ga. (450) | Wed 7/25/01 | Sat 7/28/01 |
| Build | Wed 7/25/01 | Sat 7/28/01 |
| Verify | Wed 7/25/01 | Sat 7/28/01 |
| Sign-off | Wed 7/25/01 | Sat 7/28/01 |
| Follow-up | Sat 7/28/01 | Sat 7/28/01 |
| Institution Live | Sat 7/28/01 | Sat 7/28/01 |
| Dalton (690) | Wed 7/25/01 | Sat 7/28/01 |
| Build | Wed 7/25/01 | Sat 7/28/01 |
| Verify | Wed 7/25/01 | Sat 7/28/01 |
| Sign-off | Wed 7/25/01 | Sat 7/28/01 |
| Follow-up | Sat 7/28/01 | Sat 7/28/01 |
| Institution Live | Sat 7/28/01 | Sat 7/28/01 |
| Floyd (730) | Wed 7/25/01 | Sat 7/28/01 |
| Build | Wed 7/25/01 | Sat 7/28/01 |
| Verify | Wed 7/25/01 | Sat 7/28/01 |
| Sign-off | Wed 7/25/01 | Sat 7/28/01 |
| Follow-up | Sat 7/28/01 | Sat 7/28/01 |
| Institution Live | Sat 7/28/01 | Sat 7/28/01 |
| Gainesville (750) | Wed 7/25/01 | Sat 7/28/01 |
| Build | Wed 7/25/01 | Sat 7/28/01 |
| Verify | Wed 7/25/01 | Sat 7/28/01 |
| Sign-off | Wed 7/25/01 | Sat 7/28/01 |
| Follow-up | Sat 7/28/01 | Sat 7/28/01 |
| Institution Live | Sat 7/28/01 | Sat 7/28/01 |
| Production Release Cluster 4 | Mon 7/23/01 | Fri 8/3/01 |
| Fileserver Components Packaging | Mon 7/23/01 | Fri 7/27/01 |
| Workstation Components Packaging | Mon 7/23/01 | Fri 7/27/01 |
| RCO (980) | Tue 7/31/01 | Fri 8/3/01 |
| Build | Tue 7/31/01 | Fri 8/3/01 |
| Verify | Tue 7/31/01 | Fri 8/3/01 |
| Sign-off | Tue 7/31/01 | Fri 8/3/01 |
| Follow-up | Fri 8/3/01 | Fri 8/3/01 |
| Institution Live | Fri 8/3/01 | Fri 8/3/01 |
| Augusta (270) | Tue 7/31/01 | Fri 8/3/01 |
| Build | Tue 7/31/01 | Fri 8/3/01 |
| Verify | Tue 7/31/01 | Fri 8/3/01 |
| Sign-off | Tue 7/31/01 | Fri 8/3/01 |
| Follow-up | Fri 8/3/01 | Fri 8/3/01 |
| Institution Live | Fri 8/3/01 | Fri 8/3/01 |
| East Ga. (720) | Tue 7/31/01 | Fri 8/3/01 |
| Build | Tue 7/31/01 | Fri 8/3/01 |
| Verify | Tue 7/31/01 | Fri 8/3/01 |
| Sign-off | Tue 7/31/01 | Fri 8/3/01 |
| Follow-up | Fri 8/3/01 | Fri 8/3/01 |
| Institution Live | Fri 8/3/01 | Fri 8/3/01 |
| Skidaway (930) | Tue 7/31/01 | Fri 8/3/01 |
| Build | Tue 7/31/01 | Fri 8/3/01 |
| Verify | Tue 7/31/01 | Fri 8/3/01 |
| Sign-off | Tue 7/31/01 | Fri 8/3/01 |
| Follow-up | Fri 8/3/01 | Fri 8/3/01 |
| Institution Live | Fri 8/3/01 | Fri 8/3/01 |
| Biweekly Payroll | Sat 8/4/01 | Tue 8/7/01 |
| Production Release Cluster 5 | Mon 7/30/01 | Sat 8/11/01 |
| Fileserver Components Packaging | Mon 7/30/01 | Fri 8/3/01 |
| Workstation Components Packaging | Mon 7/30/01 | Fri 8/3/01 |
| Albany (210) | Wed 8/8/01 | Sat 8/11/01 |
| Build | Wed 8/8/01 | Sat 8/11/01 |
| Verify | Wed 8/8/01 | Sat 8/11/01 |
| Sign-off | Wed 8/8/01 | Sat 8/11/01 |
| Follow-up | Sat 8/11/01 | Sat 8/11/01 |
| Institution Live | Sat 8/11/01 | Sat 8/11/01 |
| Bainbridge (620) | Wed 8/8/01 | Sat 8/11/01 |
| Build | Wed 8/8/01 | Sat 8/11/01 |
| Verify | Wed 8/8/01 | Sat 8/11/01 |
| Sign-off | Wed 8/8/01 | Sat 8/11/01 |
| Follow-up | Sat 8/11/01 | Sat 8/11/01 |
| Institution Live | Sat 8/11/01 | Sat 8/11/01 |
| Darton (700) | Wed 8/8/01 | Sat 8/11/01 |
| Build | Wed 8/8/01 | Sat 8/11/01 |
| Verify | Wed 8/8/01 | Sat 8/11/01 |
| Sign-off | Wed 8/8/01 | Sat 8/11/01 |
| Follow-up | Sat 8/11/01 | Sat 8/11/01 |
| Institution Live | Sat 8/11/01 | Sat 8/11/01 |
| South Ga. (870) | Wed 8/8/01 | Sat 8/11/01 |
| Build | Wed 8/8/01 | Sat 8/11/01 |
| Verify | Wed 8/8/01 | Sat 8/11/01 |
| Sign-off | Wed 8/8/01 | Sat 8/11/01 |
| Follow-up | Sat 8/11/01 | Sat 8/11/01 |
| Institution Live | Sat 8/11/01 | Sat 8/11/01 |
| Production Release Cluster 6 | Mon 8/6/01 | Fri 8/17/01 |
| Fileserver Components Packaging | Mon 8/6/01 | Fri 8/10/01 |
| Workstation Components Packaging | Mon 8/6/01 | Fri 8/10/01 |
| Clayton (280) | Tue 8/14/01 | Fri 8/17/01 |
| Build | Tue 8/14/01 | Fri 8/17/01 |
| Verify | Tue 8/14/01 | Fri 8/17/01 |
| Sign-off | Tue 8/14/01 | Fri 8/17/01 |
| Follow-up | Fri 8/17/01 | Fri 8/17/01 |
| Institution Live | Fri 8/17/01 | Fri 8/17/01 |
| GCSU (360) | Tue 8/14/01 | Fri 8/17/01 |
| Build | Tue 8/14/01 | Fri 8/17/01 |
| Verify | Tue 8/14/01 | Fri 8/17/01 |
| Sign-off | Tue 8/14/01 | Fri 8/17/01 |
| Follow-up | Fri 8/17/01 | Fri 8/17/01 |
| Institution Live | Fri 8/17/01 | Fri 8/17/01 |
| Gordon (760) | Tue 8/14/01 | Fri 8/17/01 |
| Build | Tue 8/14/01 | Fri 8/17/01 |
| Verify | Tue 8/14/01 | Fri 8/17/01 |
| Sign-off | Tue 8/14/01 | Fri 8/17/01 |
| Follow-up | Fri 8/17/01 | Fri 8/17/01 |
| Institution Live | Fri 8/17/01 | Fri 8/17/01 |
| Macon (810) | Tue 8/14/01 | Fri 8/17/01 |
| Build | Tue 8/14/01 | Fri 8/17/01 |
| Verify | Tue 8/14/01 | Fri 8/17/01 |
| Sign-off | Tue 8/14/01 | Fri 8/17/01 |
| Follow-up | Fri 8/17/01 | Fri 8/17/01 |
| Institution Live | Fri 8/17/01 | Fri 8/17/01 |
| Biweekly Payroll | Sat 8/18/01 | Tue 8/21/01 |
| Production Release Cluster 7 | Mon 8/13/01 | Sat 8/25/01 |
| Fileserver Components Packaging | Mon 8/13/01 | Fri 8/17/01 |
| Workstation Components Packaging | Mon 8/13/01 | Fri 8/17/01 |
| Columbus (300) | Wed 8/22/01 | Sat 8/25/01 |
| Build | Wed 8/22/01 | Sat 8/25/01 |
| Verify | Wed 8/22/01 | Sat 8/25/01 |
| Sign-off | Wed 8/22/01 | Sat 8/25/01 |
| Follow-up | Sat 8/25/01 | Sat 8/25/01 |
| Institution Live | Sat 8/25/01 | Sat 8/25/01 |
| Ft. Valley (330) | Wed 8/22/01 | Sat 8/25/01 |
| Build | Wed 8/22/01 | Sat 8/25/01 |
| Verify | Wed 8/22/01 | Sat 8/25/01 |
| Sign-off | Wed 8/22/01 | Sat 8/25/01 |
| Follow-up | Sat 8/25/01 | Sat 8/25/01 |
| Institution Live | Sat 8/25/01 | Sat 8/25/01 |
| Southwestern (420) | Wed 8/22/01 | Sat 8/25/01 |
| Build | Wed 8/22/01 | Sat 8/25/01 |
| Verify | Wed 8/22/01 | Sat 8/25/01 |
| Sign-off | Wed 8/22/01 | Sat 8/25/01 |
| Follow-up | Sat 8/25/01 | Sat 8/25/01 |
| Institution Live | Sat 8/25/01 | Sat 8/25/01 |
| Middle Ga. (840) | Wed 8/22/01 | Sat 8/25/01 |
| Build | Wed 8/22/01 | Sat 8/25/01 |
| Verify | Wed 8/22/01 | Sat 8/25/01 |
| Sign-off | Wed 8/22/01 | Sat 8/25/01 |
| Follow-up | Sat 8/25/01 | Sat 8/25/01 |
| Institution Live | Sat 8/25/01 | Sat 8/25/01 |
| Production Release Cluster 8 | Mon 8/20/01 | Fri 8/31/01 |
| Fileserver Components Packaging | Mon 8/20/01 | Fri 8/24/01 |
| Workstation Components Packaging | Mon 8/20/01 | Fri 8/24/01 |
| Atl. Metro. (610) | Tue 8/28/01 | Fri 8/31/01 |
| Build | Tue 8/28/01 | Fri 8/31/01 |
| Verify | Tue 8/28/01 | Fri 8/31/01 |
| Sign-off | Tue 8/28/01 | Fri 8/31/01 |
| Follow-up | Fri 8/31/01 | Fri 8/31/01 |
| Institution Live | Fri 8/31/01 | Fri 8/31/01 |
| Kennesaw (430) | Tue 8/28/01 | Fri 8/31/01 |
| Build | Tue 8/28/01 | Fri 8/31/01 |
| Verify | Tue 8/28/01 | Fri 8/31/01 |
| Sign-off | Tue 8/28/01 | Fri 8/31/01 |
| Follow-up | Fri 8/31/01 | Fri 8/31/01 |
| Institution Live | Fri 8/31/01 | Fri 8/31/01 |
| Sou. Poly. (500) | Tue 8/28/01 | Fri 8/31/01 |
| Build | Tue 8/28/01 | Fri 8/31/01 |
| Verify | Tue 8/28/01 | Fri 8/31/01 |
| Sign-off | Tue 8/28/01 | Fri 8/31/01 |
| Follow-up | Fri 8/31/01 | Fri 8/31/01 |
| Institution Live | Fri 8/31/01 | Fri 8/31/01 |
| Biweekly Payroll | Mon 9/3/01 | Fri 9/7/01 |