HRMS 7.51 Upgrade- Rollout Schedule

Project Start Date: Thu 8/17/00
Project Finish Date: Fri 9/7/01

Production ReleaseMon 6/11/01Fri 9/7/01
Fileserver Components PackagingMon 6/11/01Fri 6/15/01
Workstation Components Packaging Mon 6/11/01Fri 6/15/01
Fileserver/Workstation Component TestingMon 6/18/01Fri 6/29/01
Production Release Pilot - GPC (710)Mon 7/2/01Fri 7/6/01
BuildMon 7/2/01Fri 7/6/01
VerifyMon 7/2/01Fri 7/6/01
Sign-offMon 7/2/01Fri 7/6/01
Pilot LiveFri 7/6/01Fri 7/6/01
Begin Production SupportMon 7/2/01Mon 7/2/01
Biweekly PayrollSat 7/7/01Tue 7/10/01
Production Release ClustersMon 7/2/01Fri 9/7/01
Production Release Cluster 1Mon 7/2/01Sat 7/14/01
Fileserver Components PackagingMon 7/2/01Fri 7/6/01
Workstation Components Packaging Mon 7/2/01Fri 7/6/01
Southern (390)Wed 7/11/01Sat 7/14/01
BuildWed 7/11/01Sat 7/14/01
VerifyWed 7/11/01Sat 7/14/01
Sign-offWed 7/11/01Sat 7/14/01
Follow-upSat 7/14/01Sat 7/14/01
Institution LiveSat 7/14/01Sat 7/14/01
Savannah (480)Wed 7/11/01Sat 7/14/01
BuildWed 7/11/01Sat 7/14/01
VerifyWed 7/11/01Sat 7/14/01
Sign-offWed 7/11/01Sat 7/14/01
Follow-upSat 7/14/01Sat 7/14/01
Institution LiveSat 7/14/01Sat 7/14/01
Armstrong (240)Wed 7/11/01Sat 7/14/01
BuildWed 7/11/01Sat 7/14/01
VerifyWed 7/11/01Sat 7/14/01
Sign-offWed 7/11/01Sat 7/14/01
Follow-upSat 7/14/01Sat 7/14/01
Institution LiveSat 7/14/01Sat 7/14/01
West Georgia (540)Wed 7/11/01Sat 7/14/01
BuildWed 7/11/01Sat 7/14/01
VerifyWed 7/11/01Sat 7/14/01
Sign-offWed 7/11/01Sat 7/14/01
Follow-upSat 7/14/01Sat 7/14/01
Institution LiveSat 7/14/01Sat 7/14/01
Production Release Cluster 2Mon 7/9/01Fri 7/20/01
Fileserver Components PackagingMon 7/9/01Fri 7/13/01
Workstation Components Packaging Mon 7/9/01Fri 7/13/01
Valdosta (510)Tue 7/17/01Fri 7/20/01
BuildTue 7/17/01Fri 7/20/01
VerifyTue 7/17/01Fri 7/20/01
Sign-offTue 7/17/01Fri 7/20/01
Follow-upFri 7/20/01Fri 7/20/01
Institution LiveFri 7/20/01Fri 7/20/01
ABAC (570)Tue 7/17/01Fri 7/20/01
BuildTue 7/17/01Fri 7/20/01
VerifyTue 7/17/01Fri 7/20/01
Sign-offTue 7/17/01Fri 7/20/01
Follow-upFri 7/20/01Fri 7/20/01
Institution LiveFri 7/20/01Fri 7/20/01
Coastal (630)Tue 7/17/01Fri 7/20/01
BuildTue 7/17/01Fri 7/20/01
VerifyTue 7/17/01Fri 7/20/01
Sign-offTue 7/17/01Fri 7/20/01
Follow-upFri 7/20/01Fri 7/20/01
Institution LiveFri 7/20/01Fri 7/20/01
Waycross (890)Tue 7/17/01Fri 7/20/01
BuildTue 7/17/01Fri 7/20/01
VerifyTue 7/17/01Fri 7/20/01
Sign-offTue 7/17/01Fri 7/20/01
Follow-upFri 7/20/01Fri 7/20/01
Institution LiveFri 7/20/01Fri 7/20/01
Biweekly PayrollSat 7/21/01Tue 7/24/01
Production Release Cluster 3Mon 7/16/01Sat 7/28/01
Fileserver Components PackagingMon 7/16/01Fri 7/20/01
Workstation Components Packaging Mon 7/16/01Fri 7/20/01
North Ga. (450)Wed 7/25/01Sat 7/28/01
BuildWed 7/25/01Sat 7/28/01
VerifyWed 7/25/01Sat 7/28/01
Sign-offWed 7/25/01Sat 7/28/01
Follow-upSat 7/28/01Sat 7/28/01
Institution LiveSat 7/28/01Sat 7/28/01
Dalton (690)Wed 7/25/01Sat 7/28/01
BuildWed 7/25/01Sat 7/28/01
VerifyWed 7/25/01Sat 7/28/01
Sign-offWed 7/25/01Sat 7/28/01
Follow-upSat 7/28/01Sat 7/28/01
Institution LiveSat 7/28/01Sat 7/28/01
Floyd (730)Wed 7/25/01Sat 7/28/01
BuildWed 7/25/01Sat 7/28/01
VerifyWed 7/25/01Sat 7/28/01
Sign-offWed 7/25/01Sat 7/28/01
Follow-upSat 7/28/01Sat 7/28/01
Institution LiveSat 7/28/01Sat 7/28/01
Gainesville (750)Wed 7/25/01Sat 7/28/01
BuildWed 7/25/01Sat 7/28/01
VerifyWed 7/25/01Sat 7/28/01
Sign-offWed 7/25/01Sat 7/28/01
Follow-upSat 7/28/01Sat 7/28/01
Institution LiveSat 7/28/01Sat 7/28/01
Production Release Cluster 4Mon 7/23/01Fri 8/3/01
Fileserver Components PackagingMon 7/23/01Fri 7/27/01
Workstation Components Packaging Mon 7/23/01Fri 7/27/01
RCO (980)Tue 7/31/01Fri 8/3/01
BuildTue 7/31/01Fri 8/3/01
VerifyTue 7/31/01Fri 8/3/01
Sign-offTue 7/31/01Fri 8/3/01
Follow-upFri 8/3/01Fri 8/3/01
Institution LiveFri 8/3/01Fri 8/3/01
Augusta (270)Tue 7/31/01Fri 8/3/01
BuildTue 7/31/01Fri 8/3/01
VerifyTue 7/31/01Fri 8/3/01
Sign-offTue 7/31/01Fri 8/3/01
Follow-upFri 8/3/01Fri 8/3/01
Institution LiveFri 8/3/01Fri 8/3/01
East Ga. (720)Tue 7/31/01Fri 8/3/01
BuildTue 7/31/01Fri 8/3/01
VerifyTue 7/31/01Fri 8/3/01
Sign-offTue 7/31/01Fri 8/3/01
Follow-upFri 8/3/01Fri 8/3/01
Institution LiveFri 8/3/01Fri 8/3/01
Skidaway (930)Tue 7/31/01Fri 8/3/01
BuildTue 7/31/01Fri 8/3/01
VerifyTue 7/31/01Fri 8/3/01
Sign-offTue 7/31/01Fri 8/3/01
Follow-upFri 8/3/01Fri 8/3/01
Institution LiveFri 8/3/01Fri 8/3/01
Biweekly PayrollSat 8/4/01Tue 8/7/01
Production Release Cluster 5Mon 7/30/01Sat 8/11/01
Fileserver Components PackagingMon 7/30/01Fri 8/3/01
Workstation Components Packaging Mon 7/30/01Fri 8/3/01
Albany (210)Wed 8/8/01Sat 8/11/01
BuildWed 8/8/01Sat 8/11/01
VerifyWed 8/8/01Sat 8/11/01
Sign-offWed 8/8/01Sat 8/11/01
Follow-upSat 8/11/01Sat 8/11/01
Institution LiveSat 8/11/01Sat 8/11/01
Bainbridge (620)Wed 8/8/01Sat 8/11/01
BuildWed 8/8/01Sat 8/11/01
VerifyWed 8/8/01Sat 8/11/01
Sign-offWed 8/8/01Sat 8/11/01
Follow-upSat 8/11/01Sat 8/11/01
Institution LiveSat 8/11/01Sat 8/11/01
Darton (700)Wed 8/8/01Sat 8/11/01
BuildWed 8/8/01Sat 8/11/01
VerifyWed 8/8/01Sat 8/11/01
Sign-offWed 8/8/01Sat 8/11/01
Follow-upSat 8/11/01Sat 8/11/01
Institution LiveSat 8/11/01Sat 8/11/01
South Ga. (870)Wed 8/8/01Sat 8/11/01
BuildWed 8/8/01Sat 8/11/01
VerifyWed 8/8/01Sat 8/11/01
Sign-offWed 8/8/01Sat 8/11/01
Follow-upSat 8/11/01Sat 8/11/01
Institution LiveSat 8/11/01Sat 8/11/01
Production Release Cluster 6Mon 8/6/01Fri 8/17/01
Fileserver Components PackagingMon 8/6/01Fri 8/10/01
Workstation Components Packaging Mon 8/6/01Fri 8/10/01
Clayton (280)Tue 8/14/01Fri 8/17/01
BuildTue 8/14/01Fri 8/17/01
VerifyTue 8/14/01Fri 8/17/01
Sign-offTue 8/14/01Fri 8/17/01
Follow-upFri 8/17/01Fri 8/17/01
Institution LiveFri 8/17/01Fri 8/17/01
GCSU (360)Tue 8/14/01Fri 8/17/01
BuildTue 8/14/01Fri 8/17/01
VerifyTue 8/14/01Fri 8/17/01
Sign-offTue 8/14/01Fri 8/17/01
Follow-upFri 8/17/01Fri 8/17/01
Institution LiveFri 8/17/01Fri 8/17/01
Gordon (760)Tue 8/14/01Fri 8/17/01
BuildTue 8/14/01Fri 8/17/01
VerifyTue 8/14/01Fri 8/17/01
Sign-offTue 8/14/01Fri 8/17/01
Follow-upFri 8/17/01Fri 8/17/01
Institution LiveFri 8/17/01Fri 8/17/01
Macon (810)Tue 8/14/01Fri 8/17/01
BuildTue 8/14/01Fri 8/17/01
VerifyTue 8/14/01Fri 8/17/01
Sign-offTue 8/14/01Fri 8/17/01
Follow-upFri 8/17/01Fri 8/17/01
Institution LiveFri 8/17/01Fri 8/17/01
Biweekly PayrollSat 8/18/01Tue 8/21/01
Production Release Cluster 7Mon 8/13/01Sat 8/25/01
Fileserver Components PackagingMon 8/13/01Fri 8/17/01
Workstation Components Packaging Mon 8/13/01Fri 8/17/01
Columbus (300)Wed 8/22/01Sat 8/25/01
BuildWed 8/22/01Sat 8/25/01
VerifyWed 8/22/01Sat 8/25/01
Sign-offWed 8/22/01Sat 8/25/01
Follow-upSat 8/25/01Sat 8/25/01
Institution LiveSat 8/25/01Sat 8/25/01
Ft. Valley (330)Wed 8/22/01Sat 8/25/01
BuildWed 8/22/01Sat 8/25/01
VerifyWed 8/22/01Sat 8/25/01
Sign-offWed 8/22/01Sat 8/25/01
Follow-upSat 8/25/01Sat 8/25/01
Institution LiveSat 8/25/01Sat 8/25/01
Southwestern (420)Wed 8/22/01Sat 8/25/01
BuildWed 8/22/01Sat 8/25/01
VerifyWed 8/22/01Sat 8/25/01
Sign-offWed 8/22/01Sat 8/25/01
Follow-upSat 8/25/01Sat 8/25/01
Institution LiveSat 8/25/01Sat 8/25/01
Middle Ga. (840)Wed 8/22/01Sat 8/25/01
BuildWed 8/22/01Sat 8/25/01
VerifyWed 8/22/01Sat 8/25/01
Sign-offWed 8/22/01Sat 8/25/01
Follow-upSat 8/25/01Sat 8/25/01
Institution LiveSat 8/25/01Sat 8/25/01
Production Release Cluster 8Mon 8/20/01Fri 8/31/01
Fileserver Components PackagingMon 8/20/01Fri 8/24/01
Workstation Components Packaging Mon 8/20/01Fri 8/24/01
Atl. Metro. (610)Tue 8/28/01Fri 8/31/01
BuildTue 8/28/01Fri 8/31/01
VerifyTue 8/28/01Fri 8/31/01
Sign-offTue 8/28/01Fri 8/31/01
Follow-upFri 8/31/01Fri 8/31/01
Institution LiveFri 8/31/01Fri 8/31/01
Kennesaw (430)Tue 8/28/01Fri 8/31/01
BuildTue 8/28/01Fri 8/31/01
VerifyTue 8/28/01Fri 8/31/01
Sign-offTue 8/28/01Fri 8/31/01
Follow-upFri 8/31/01Fri 8/31/01
Institution LiveFri 8/31/01Fri 8/31/01
Sou. Poly. (500)Tue 8/28/01Fri 8/31/01
BuildTue 8/28/01Fri 8/31/01
VerifyTue 8/28/01Fri 8/31/01
Sign-offTue 8/28/01Fri 8/31/01
Follow-upFri 8/31/01Fri 8/31/01
Institution LiveFri 8/31/01Fri 8/31/01
Biweekly PayrollMon 9/3/01Fri 9/7/01